Rs 25,01,400 crore worth infrastructure projects: These projects witnessed a cost overrun of Rs 4.77 lakh crore!

Rs 25,01,400 crore worth infrastructure projects: These projects witnessed a cost overrun of Rs 4.77 lakh crore!

Karan Dsij
/ Categories: Trending, Mindshare

They are now projected to cost Rs 29,78,681.31 crore in total, indicating a substantial cost overrun of Rs 4,77,280.69 crore

In August of this year, India found itself at the crossroads of ambition and challenge as it grappled with a staggering infrastructure puzzle. Picture this: 412 monumental infrastructure projects, each demanding an investment of over Rs 150 crore, stood as both monuments to progress and harbingers of fiscal complexity. This monumental tangle of projects, a vital heartbeat for the nation's growth, carried a heavy burden—a cost overrun of Rs 4.77 lakh crore, a figure that could redefine the future landscape of India's development.

Screenshot-2023-09-25-174218

Source: Ministry of Statistics and Programme Implementation

From the hallowed halls of the Ministry of Statistics and Programme Implementation, this astonishing revelation spilled forth. In their latest report, they unveiled the startling truth: the initial cost of 1762 projects were Rs 25,01,400.62 crore, but they are now projected to cost Rs 29,78,681.31 crore in total, indicating a substantial cost overrun of Rs 4,77,280.69 crore, equivalent to 19.08 per cent of the original estimate.

But it wasn't just about the financial tremors that shook the nation. This report also chronicles the relentless march of time, showcasing how 830 projects had been caught in the web of delays. A staggering 52.28 per cent of the expected project costs, a whopping Rs 15,57,188.10 crore, had already been spent on these massive endeavors, highlighting the nation's dedication. However, even the most optimistic eyes widened at the revelation that the delays, when calculated based on the most recent completion schedules, reduced the count to 624.

Beneath the numbers and calculations lies a tale of intrigue and complexity. Among these ambitious undertakings, 339 projects dared to defy the confines of timelines and expectations, refusing to reveal their expected commissioning year or tentative gestation period. For those that did offer insight into their delays, the range was vast - from minor hiccups of 1 to 12 months to monumental postponements stretching over 60 months. The average delay for these 830 projects stood at a staggering 36.96 months, painting a vivid picture of the labyrinthine challenges they faced.

So why the delays? The report did not mince words. Land acquisition woes, environmental clearances snarled in bureaucratic mazes, and a severe dearth of infrastructure support had held these projects hostage. Beyond these, securing financing, nailing down detailed engineering, navigating scope changes, tendering, ordering, and equipment supply—each acted as a formidable barrier on the path to progress. Adding further layers of complexity, issues of law and order cast shadows that extended timelines. The COVID-19 pandemic, with its state lockdowns in 2020 and 2021, only served to compound the troubles in project execution.

DSIJ’s ‘Flash News Investment' weekly Newsletter recommends profit-making ideas for you based on fundamental and technical analysis. If this interests you, do download the service details here.

And here's the kicker: the report hinted at a lurking enigma. It suggested that some project execution agencies may not have been entirely forthcoming with revised cost estimates and commissioning schedules for multiple projects. This raised a tantalizing question—could the time and cost overrun data be a mere fraction of the truth?

Fast forward to July 2023, and the nation held its breath once more. The ministry's report for the month unveiled yet another striking figure: 388 infrastructure projects bore the weight of cost overruns exceeding Rs 4.65 lakh crore, as if to remind us that the enigma continues to unravel.

In the labyrinth of India's infrastructure aspirations, this tale of cost overruns and delays is a symphony of ambition and challenge, echoing the nation's relentless pursuit of progress and the myriad obstacles that stand in its way. It is a story that captivates the imagination, beckoning us to witness the ongoing drama of India's development unfold.

Previous Article Penny Stocks: Stocks likely to be in focus tomorrow!
Next Article Vijay Kedia gains Rs 4,83,31,875 from this multibagger penny stock below Rs 100 in just 21 days with robust order book worth Rs 2,961 crore; Do you own it?
Rate this article:
4.2

DALAL STREET INVESTMENT JOURNAL - DEMOCRATIZING WEALTH CREATION

Principal Officer: Mr. Shashikant Singh,
Email: principalofficer@dsij.in
Tel: (+91)-20-66663800

Compliance Officer: Mr. Rajesh Padode
Email: complianceofficer@dsij.in
Tel: (+91)-20-66663800

Grievance Officer: Mr. Rajesh Padode
Email: service@dsij.in
Tel: (+91)-20-66663800

Corresponding SEBI regional/local office address- SEBI Bhavan BKC, Plot No.C4-A, 'G' Block, Bandra-Kurla Complex, Bandra (East), Mumbai - 400051, Maharashtra.
Tel: +91-22-26449000 / 40459000 | Fax : +91-22-26449019-22 / 40459019-22 | E-mail : sebi@sebi.gov.in | Toll Free Investor Helpline: 1800 22 7575 | SEBI SCORES | SMARTODR